A 2024 arrival with one building standing

QUBE Development registered with the Dubai Land Department as developer № 1692 in August 2023 and announced itself publicly in June 2024, with a portfolio it then valued at AED 2.6 billion across 2,291,946 sq ft of gross floor area. Two and a half years later the pipeline it publishes is AED 7.5 billion across six projects in Dubai and Ras Al Khaimah by the end of 2027, on 1,154,704 sq ft of land. The chief executive is Egor Molchanov.

What has actually been delivered

One building. Cubix Residences in Jumeirah Village Circle — studios through three-bedroom duplexes, smart-home automation, a pool, gym, sauna and ground-floor retail — sold out before completion and was handed over in April 2026, on time — one project completed, none late and none overdue. Arisha Terraces, 419 apartments in four low-rise buildings in Dubai Studio City, is in construction for Q4 2027 with three of its four phases sold out. ELIRE Managed by LUX*, 100 branded residences in Business Bay operated by The Lux Collective and built by ASGC, is in construction for Q4 2028.

One project has been cancelled. MIDORA Residences, a 49-storey, 492-home tower in JVC District 13 designed by Nikken Sekkei and launched in September 2024, did not proceed; Binghatti Circle was later launched on the same plot. It stays on this page because a buyer weighing an off-plan purchase is entitled to the whole list.

Meydan Horizon — the current project

GRAF sells SAWA Residences, launched on 3 November 2026 and QUBE's first building on water. Three hundred and fifty-five apartments over twenty residential floors on one of the longest lagoon frontages in Meydan Horizon, Mohammed Bin Rashid City: 246 one-bedrooms, 91 two-bedrooms and just 18 three-bedrooms, from AED 1,050,000 on a 60/40 plan with handover scheduled for Q1 2030. DLD project 4565, escrow at Dubai Islamic Bank, architect KEO International Consultants. Bosch kitchen appliances and Synchro smart lighting come as standard in every home.

Sources: QUBE — Who We Are, QUBE — SAWA Residences, Zawya — QUBE hands over inaugural project in JVC, and Propsearch — Qube Development.

Entered Dubai in 2024, delivered its first building on time in 2026, and is now selling on the Meydan Horizon lagoon

Meydan horizonMbr cityWaterfrontBranded residencesNew developer

Who owns QUBE Development?

The developing entity is Qube Development LLC, privately owned, registered with the Dubai Land Department as developer № 1692 as of August 2023 and licensed by the Dubai Economic Department under licence 1043390. Egor Molchanov is Chief Executive; the senior team is Ramy Abdel Kader (Construction Director), Asmae Boussouf (Commercial Director), Andrey Lazarev (Development Director), Polina Iurikova (Strategy and Operations Director) and Christel Esterhuizen (Human Resources).

QUBE names no individual or parent shareholder publicly, and GRAF does not infer one.

One thing worth stating plainly, because the name invites it: the 30 years and the three decades of development legacy belong to the wider group behind the company. The UAE development record starts in June 2024, and it is its own number.

Source: Qube Development — Propsearch company record · QUBE Development — Who We Are · Major new player enters property market with AED 2.6bn project pipeline

Track record

Buildings that made the name

  1. 01 Registered with the Dubai Land Department Qube Development LLC is recorded as DLD developer № 1692, under Dubai Economic Department licence 1043390. The registration predates the public launch by ten months, which is the window in which the land was assembled; the first project, MIDORA, first appears in November 2023. August 2023
  2. 02 Entry into the UAE market with AED 2.6 billion QUBE announced itself in Dubai with a portfolio it valued at AED 2.6 billion, covering 2,291,946 sq ft of gross floor area and a land bank of 623,354 sq ft. Both figures have since grown to 1,154,704 sq ft of land, 3,716,324 sq ft of GFA and AED 7.5 billion of launches by 2027. June 2024
  3. 03 MIDORA Residences launched in JVC A 49-storey, 492-home tower in JVC District 13 designed by Nikken Sekkei, with studios from AED 619,000 and three-bedroom duplexes to 2,946 sq ft, valued on the Land Department register at AED 306,776,000. It was the company's first launch — and it was later cancelled. Binghatti Circle was subsequently launched on the same plot. September 2024
  4. 04 Arisha Terraces launched in Dubai Studio City Four low-rise B+G+8 buildings with 419 apartments around a planted central courtyard, with a rooftop hydroponic garden, padel court, cinema, yoga spaces and co-working. Construction began in January 2025; phases one, two and three are sold out and phase four is the current release, with completion set for Q4 2027. October 2024
  5. 05 Partnership with The Lux Collective QUBE and The Lux Collective announced ELIRE Managed by LUX* — 100 branded residences on Burj Khalifa Boulevard in Business Bay, one to three bedrooms plus three and four-bedroom duplexes, with concierge, valet, in-residence dining and housekeeping. The project broke ground in August 2025. June 2025
  6. 06 ASGC appointed main contractor for ELIRE QUBE named ASGC Construction as main contractor for ELIRE, with handover scheduled for the fourth quarter of 2028. Foundation casting began in August 2026. ASGC is one of the larger contractors in the UAE. May 2026
  7. 07 Cubix Residences handed over — the first delivery The company's inaugural residential building, in Jumeirah Village Circle: studios through three-bedroom duplexes with smart-home automation, integrated security, branded kitchen appliances and private pools on the duplex terraces, over a swimming pool, gym, sauna and ground-floor retail. It sold out ahead of completion and was handed over on time, and a buyer can walk into it today. Delivered April 2026
  8. 08 SAWA Residences launched at Meydan Horizon Three hundred and fifty-five one, two and three-bedroom apartments on one of the longest lagoon frontages in Meydan Horizon, Mohammed Bin Rashid City — DLD project 4565, from AED 1,050,000 on a 60/40 plan with handover scheduled for Q1 2030. It is QUBE's first project in MBR City and its first on water. 3 November 2026

QUBE track record: delivered and under construction

Buildings handed over
1
Cubix Residences, Jumeirah Village Circle — April 2026, sold out before completion
On-time delivery rate
100%
1 completed, 0 late, 0 overdue as of November 2026
UAE market entry
June 2024
Announced with an AED 2.6 billion portfolio; DLD developer registration dates to August 2023
DLD developer number
1692
Recorded as of August 2023; DED licence 1043390

Delivered Under construction

Two records, counted separately, because they are not the same thing. The 30 years belong to the wider group behind the company.The UAE record begins in June 2024 and, as of November 2026, is one completed building — Cubix Residences in JVC, handed over in April 2026 and sold out before it was finished. One project completed, none late, none overdue. One project was cancelled, and it is listed here with the rest.

Project Area Type Status Date
Cubix Residences Jumeirah Village Circle, Dubai Studios to 3-bedroom duplexes, smart-home fitted — the company's first UAE building Delivered April 2026
MIDORA Residences JVC District 13, Dubai 49 storeys, 492 homes, designed by Nikken Sekkei — launched September 2024 Cancelled Cancelled
Arisha Terraces Dubai Studio City, Dubai 419 apartments in four low-rise B+G+8 buildings — phases 1 to 3 sold out Under construction Q4 2027
ELIRE Managed by LUX* Business Bay, Dubai 100 branded residences with The Lux Collective; main contractor ASGC Under construction Q4 2028
SAWA Residences Meydan Horizon, MBR City, Dubai 355 apartments on the lagoon frontage, 1 to 3 bedrooms, DLD project 4565 Selling Q1 2030
Arisha Terraces 2 Dubai Studio City, Dubai Second phase of the Studio City community — registered, not yet launched publicly Planned Not announced

Source: QUBE Development — Our Projects, and its dated press releases · checked 21 November 2026

What QUBE is known for

Its first building was delivered, and on time
Cubix Residences, Jumeirah Village Circle, handed over April 2026 — sold out before completion, with no late or overdue projects behind it
A major contractor on the flagship
ASGC Construction appointed main contractor for ELIRE Managed by LUX*, May 2026, with foundation casting from August 2026
A hospitality operator on the branded line
The Lux Collective manages ELIRE's 100 residences in Business Bay — an operator agreement, not a licensed name
Registered with the Land Department before it launched
DLD developer № 1692 from August 2023, DED licence 1043390, ten months before the first public launch
Published pipeline with named numbers
AED 7.5 billion of launches by 2027 across six projects in Dubai and Ras Al Khaimah, on 1,154,704 sq ft of land and 3,716,324 sq ft of GFA
Ranked 34th among the UAE's real-estate icons
The Finance World's Top 150 real-estate icons of the UAE, 2025

The delivery record is one building. Everything else above is a commitment, a contract or a registration rather than a completion, which is what two and a half years of selling in Dubai buys.The 30 years belong to the group behind the company; the delivery record is its own number.

The handover of Cubix Residences reflects our teams' work over the last two and a half years, and we are all very proud of what we have achieved. At QUBE Development, we have the full confidence in the UAE's leadership and the strength of Dubai's residential market. We remain focused on delivering our current developments as planned and launching new projects in 2026.
Egor Molchanov Chief Executive, QUBE Development Zawya, 15 April 2026

Where QUBE builds

Current projects via GRAF

QUBE prices, payment plans and handover dates

GRAF sells SAWA Residences.Cubix Residences is handed over and sold out, so it is no longer developer stock; Arisha Terraces has sold phases one to three and releases phase four directly; ELIRE Managed by LUX* is QUBE's branded-residence line in Business Bay.

Project Area Type Price from Payment plan Handover Availability
SAWA Residences Meydan Horizon, MBR City 1, 2 and 3-bedroom waterfront apartments, Bosch-fitted kitchens AED 1,050,000 60/40 Q1 2030 Selling

Prices, payment plans, handover dates and availability verified by GRAF on 21 November 2026. Each row links to the project page, where the same figures are shown in full.

How QUBE differs from other Dubai developers

QUBE arrived in Dubai in June 2024, in the same wave as a long list of new names. Three things separate it from most of them, and they are all checkable: it had already registered with the Land Department before it launched, its first building came in on time, and it put a tier-one contractor and an international hotel operator on its flagship rather than running everything in-house.

The first delivery landed on schedule
Cubix Residences in JVC was launched into the 2024 programme, sold out before it was finished and handed over in April 2026 — one project completed, none late and none overdue. For a company this young that single data point is worth more than the whole pipeline figure.
An international operator runs the branded line
ELIRE Managed by LUX* is operated by The Lux Collective, the hospitality group behind the LUX* brand, across 100 residences on Burj Khalifa Boulevard — concierge, valet, in-residence dining and housekeeping included. That is a management agreement with a working hotel company, not a name licensed onto a facade.
ASGC builds the flagship
The main contractor for ELIRE is ASGC Construction, appointed in May 2026, with the first portion of the foundation cast in August 2026. A new developer choosing an established contractor over the cheapest tender is the kind of decision that shows up at handover rather than at launch.
Every project sits inside an established district
Jumeirah Village Circle, Dubai Studio City, Business Bay and now Meydan Horizon in MBR City. None of it is on the edge of the map, which means a buyer can check comparable sales and rents on the same street rather than waiting for a community to exist.
The amenity programmes are unusually long for the price
Arisha Terraces carries a rooftop hydroponic garden, padel court, cinema, co-working and indoor and outdoor yoga across four low-rise buildings. SAWA adds two pools plus a children's pool, a solarium with cabanas, a Zen garden, a boxing corner, a cinema room and a virtual-reality corner. On a one-bedroom entry of AED 1.05M that list is the product.
The commercial package comes in figures, not adjectives
Land area 1,154,704 sq ft, gross floor area 3,716,324 sq ft, AED 7.5 billion of launches by 2027, six projects and a completion date on each one. A buyer gets numbers to check rather than claims to believe.
Why GRAF recommends QUBE

GRAF sells SAWA Residences. QUBE Development suits a buyer who wants a lagoon-front apartment in Mohammed Bin Rashid City from AED 1,050,000, bought from a young Dubai developer whose first building was handed over on time and whose flagship is built by ASGC and run by an international hotel operator.

What the record shows
  1. The delivery claim is recent and checkableCubix Residences in Jumeirah Village Circle, handed over in April 2026 after selling out ahead of completion. One project completed, none late and none overdue as of November 2026.
  2. SAWA carries a full commercial package355 apartments on DLD project 4565, escrow 001640264976701 at Dubai Islamic Bank. One-bedrooms of 390 to 744 sq ft from AED 1,050,000, two-bedrooms of 891 to 1,279 sq ft from AED 2,410,000, three-bedrooms of 1,254 to 1,558 sq ft from AED 3,080,000, Bosch kitchens and smart lighting as standard, a 60/40 headline plan and handover scheduled for Q1 2030.
  3. The whole project list is on the page, cancellation includedThe UAE development record is one completed building, not thirty years of them. MIDORA Residences, a 492-home tower launched in JVC in September 2024, was cancelled, and Binghatti Circle was launched on the same plot. It sits in the track record above alongside the deliveries, because a buyer weighing an off-plan purchase is entitled to the whole list.

GRAF editorial team

QUBE — frequently asked questions

Who owns QUBE Development?

The developing entity is Qube Development LLC, privately owned and registered with the Dubai Land Department as developer № 1692 as of August 2023 under Dubai Economic Department licence 1043390. Egor Molchanov is Chief Executive. QUBE names no individual or parent shareholder publicly, and GRAF does not name one.

Source: Qube Development — Propsearch developer record

What has QUBE Development actually completed?

One building. Cubix Residences in Jumeirah Village Circle — studios through three-bedroom duplexes with smart-home automation, a swimming pool, gym, sauna and ground-floor retail — sold out before completion and was handed over in April 2026. It is the company's inaugural UAE delivery. Arisha Terraces in Dubai Studio City and ELIRE Managed by LUX* in Business Bay are in construction for Q4 2027 and Q4 2028.

Source: UAE: QUBE Development hands over inaugural project in JVC

When was QUBE Development founded?

Qube Development LLC was registered with the Dubai Land Department in August 2023 and announced its entry into the UAE market in June 2024 with an AED 2.6 billion portfolio. The 30 years and the three decades of development legacy belong to the wider group behind it. The UAE record begins in 2024 and is one handover so far.

Source: QUBE Development has entered Dubai's booming real estate market

Has QUBE Development ever cancelled a project?

Yes, once. MIDORA Residences — a 49-storey, 492-home tower in JVC District 13 designed by Nikken Sekkei, launched in September 2024 with studios from AED 619,000 — was cancelled, and Binghatti Circle was later launched on the same plot. It was QUBE's first launch, and it stays in the track record on this page.

Source: Midora Residences — Propsearch building guide

What is QUBE Development selling at Meydan Horizon?

SAWA Residences: 355 one, two and three-bedroom apartments on one of the longest lagoon frontages in Meydan Horizon, Mohammed Bin Rashid City, DLD project 4565. One-bedrooms of 390 to 744 sq ft from AED 1,050,000, two-bedrooms of 891 to 1,279 sq ft from AED 2,410,000 and three-bedrooms of 1,254 to 1,558 sq ft from AED 3,080,000, all with Bosch kitchen appliances and Synchro smart lighting, on a 60/40 payment plan with handover scheduled for Q1 2030.

Source: SAWA Residences — official QUBE project page

Who builds QUBE's projects?

ASGC Construction was appointed main contractor for ELIRE Managed by LUX* in May 2026, and the first portion of the foundation was cast in August 2026. The Lux Collective, the hospitality group behind the LUX* brand, manages the residences there. The architect for SAWA Residences is KEO International Consultants.

Source: Sawa Residences — Propsearch building guide

Guides that cover this developer

About this profile

Maintained by the GRAF editorial team from public sources and our own project data. Updated 21 November 2026. Contact us

Get the Brochure

We'll send it to your WhatsApp shortly.